MISO request S1127
MISO queue ID S1127
Queue request S1127 was listed in the MISO interconnection queue at the end of 2025 as a 170 MW battery project in Washington County, MS, according to Berkeley Lab’s queue data file. The filing names GERALD ANDRUS SES SWYD - TINNIN ROAD as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of June 1, 2027.
| Queue ID | S1127 |
|---|---|
| Project name | Not reported |
| Status (as published) | Active |
| Substation | GERALD ANDRUS SES SWYD - TINNIN ROAD |
| Point of interconnection | GERALD ANDRUS SES SWYD - TINNIN ROAD 230.0kV |
| County | Washington |
| State | MS |
| Voltage | 230 kV |
| Capacity | 170 MW |
| Resource (as published) | Battery |
| Resource category | Battery (normalized for filtering) |
| Proposed online date | 2027-06-01 |
| Source dataset | Berkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025 |
Same substation and county
Washington, MS: 11 requests in the MISO queue, 3 active totaling 670 MW.
Tracked changes
Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.
Additional filed fields
| Utility | ENTERGY MISSISSIPPI, LLC. |
|---|---|
| Project type | Generation |
| Queue date | 2025-11-10 |
Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.
Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.