Surplus; J944

MISO queue ID S1117

Surplus; J944 (S1117) was listed in the MISO interconnection queue at the end of 2025 as a 200 MW battery project in New Madrid County, MO, according to Berkeley Lab’s queue data file. The filing names Marston as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of June 1, 2028.

Queue IDS1117
Project nameSurplus; J944
Status (as published)Active
SubstationMarston
Point of interconnectionMarston 161 kV
CountyNew Madrid
StateMO
Voltage161 kV
Capacity200 MW
Resource (as published)Battery
Resource categoryBattery (normalized for filtering)
Proposed online date2028-06-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

New Madrid, MO: 4 requests in the MISO queue, 3 active totaling 550 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityENTERGY ARKANSAS
Project typeGeneration
Queue date2025-08-31

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.