Substation Scout

Surplus; J992

MISO queue ID S1102

Surplus; J992 (S1102) was listed in the MISO interconnection queue at the end of 2025 as a 200 MW battery project in Cass County, IN, according to Berkeley Lab’s queue data file. The filing names Walton 230 as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of June 30, 2026.

Queue IDS1102
Project nameSurplus; J992
Status (as published)Active
SubstationWalton 230
Point of interconnectionWalton 230
CountyCass
StateIN
VoltageNot reported
Capacity200 MW
Resource (as published)Battery
Resource categoryBattery (normalized for filtering)
Proposed online date2026-06-30
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Cass, IN: 7 requests in the MISO queue, 3 active totaling 404 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityDUKE ENERGY INDIANA
Project typeGeneration
Queue date2025-06-16

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first