Surplus; J1450 (S1073) was listed in the MISO interconnection queue at the end of 2025 as a 150 MW hybrid project in Webster County, KY, according to Berkeley Lab’s queue data file. The filing names Hopkins to Reid EVH as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of August 31, 2026.
| Queue ID | S1073 |
|---|---|
| Project name | Surplus; J1450 |
| Status (as published) | Active |
| Substation | Hopkins to Reid EVH |
| Point of interconnection | Hopkins to Reid EVH 161kV |
| County | Webster |
| State | KY |
| Voltage | 161 kV |
| Capacity | 150 MW |
| Resource (as published) | Other+Battery |
| Resource category | Hybrid (normalized for filtering) |
| Proposed online date | 2026-08-31 |
| Source dataset | Berkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025 |
Same substation and county
Webster, KY: 7 requests in the MISO queue, 3 active totaling 460 MW.
Tracked changes
Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.
Additional filed fields
| Utility | BIG RIVERS ELECTRIC CORPORATION |
|---|---|
| Project type | Generation |
| Queue date | 2025-02-19 |
| Components (hybrid) | Other 150 MW + Battery |
Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.
Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.