Surplus; J199/J202 (S1059) was listed in the MISO interconnection queue at the end of 2025 as a 100.3 MW hybrid project in Tuscola County, MI, according to Berkeley Lab’s queue data file. The filing names Dixon - Bus # as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of November 18, 2013.

Queue IDS1059
Project nameSurplus; J199/J202
Status (as published)Active
SubstationDixon - Bus #
Point of interconnectionDixon 120kV - Bus # 265182
CountyTuscola
StateMI
Voltage120 kV
Capacity100.3 MW
Resource (as published)Other+Battery
Resource categoryHybrid (normalized for filtering)
Proposed online date2013-11-18
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Tuscola, MI: 25 requests in the MISO queue, 15 active totaling 2,038.6 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityITC
Project typeGeneration
Queue date2024-07-26
Components (hybrid)Other 100.3 MW + Battery

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first