Substation Scout

Surplus; J1386

MISO queue ID S1044

Surplus; J1386 (S1044) was listed in the MISO interconnection queue at the end of 2025 as a 50 MW hybrid project in Lake County, IN, according to Berkeley Lab’s queue data file. The filing names Green Acres Substation as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of April 7, 2024.

Queue IDS1044
Project nameSurplus; J1386
Status (as published)Active
SubstationGreen Acres Substation
Point of interconnectionGreen Acres 138 kV Substation (43684)
CountyLake
StateIN
Voltage138 kV
Capacity50 MW
Resource (as published)Other+Battery
Resource categoryHybrid (normalized for filtering)
Proposed online date2024-04-07
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Lake, IN: 9 requests in the MISO queue, 7 active totaling 1,426.7 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityNORTHERN INDIANA PUBLIC SERVICE COMPANY
Project typeGeneration
Queue date2023-04-17
Components (hybrid)Other 50 MW + Battery

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first