MISO request R26
MISO queue ID R26
Queue request R26 was listed in the MISO interconnection queue at the end of 2025 as a 400 MW wind project in Atchison County, MO, according to Berkeley Lab’s queue data file. The filing names MEC Cooper - Booneville as its point of interconnection. Its status as of December 31, 2025 was “Operational”.
| Queue ID | R26 |
|---|---|
| Project name | Not reported |
| Status (as published) | Operational |
| Substation | MEC Cooper - Booneville |
| Point of interconnection | MEC Cooper - Booneville 345 kV |
| County | Atchison |
| State | MO |
| Voltage | 345 kV |
| Capacity | 400 MW |
| Resource (as published) | Wind |
| Resource category | Wind (normalized for filtering) |
| Proposed online date | Not reported |
| Source dataset | Berkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025 |
Same substation and county
Atchison, MO: 4 requests in the MISO queue, 2 active totaling 646 MW.
Tracked changes
Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.
Additional filed fields
| Project type | Generation |
|---|---|
| Study phase (standardized by Berkeley Lab) | IA Executed |
| Queue date | 2006-02-28 |
| Interconnection agreement date | 2015-06-16 |
Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.
Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.