Substation Scout

Replacing 864 MW of coal with Natural Gas Generators; Castle Bluff

MISO queue ID R1047

Replacing 864 MW of coal with Natural Gas Generators; Castle Bluff (R1047) was listed in the MISO interconnection queue at the end of 2025 as a 824 MW hybrid project in St. Louis County, MO, according to Berkeley Lab’s queue data file. The filing names Meramec Substation as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of December 31, 2025.

Queue IDR1047
Project nameReplacing 864 MW of coal with Natural Gas Generators; Castle Bluff
Status (as published)Active
SubstationMeramec Substation
Point of interconnectionMeramec Substation 138kV
CountySt. Louis
StateMO
Voltage138 kV
Capacity824 MW
Resource (as published)Gas+Other
Resource categoryHybrid (normalized for filtering)
Proposed online date2025-12-31
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

St. Louis, MO: 2 requests in the MISO queue, 2 active totaling 922.8 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityAMEREN MISSOURI
Interconnection serviceNRIS
Project typeGeneration
Queue date2024-05-28
Components (hybrid)Gas 824 MW + Other

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.