Substation Scout

Replacing 258MW ERIS gas/oil with 237MW ERIS Natural Gas/oil; Wheaton 1-4

MISO queue ID R1045

Replacing 258MW ERIS gas/oil with 237MW ERIS Natural Gas/oil; Wheaton 1-4 (R1045) was listed in the MISO interconnection queue at the end of 2025 as a 237 MW hybrid project in Chippewa County, MN, according to Berkeley Lab’s queue data file. The filing names Wheaton as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of June 3, 2025.

Queue IDR1045
Project nameReplacing 258MW ERIS gas/oil with 237MW ERIS Natural Gas/oil; Wheaton 1-4
Status (as published)Active
SubstationWheaton
Point of interconnectionWheaton 161kV
CountyChippewa
StateMN
Voltage161 kV
Capacity237 MW
Resource (as published)Gas+Other
Resource categoryHybrid (normalized for filtering)
Proposed online date2025-06-03
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Chippewa, MN: 3 requests in the MISO queue, 1 active totaling 237 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityNORTHERN STATES POWER COMPANY
Interconnection serviceNRIS
Project typeGeneration
Queue date2024-03-01
Components (hybrid)Gas 237 MW + Other

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first