Replacing 30 MW of existing coal generation with BESS at Burlington Generation Station; Burlington 5 (R1019) was listed in the MISO interconnection queue at the end of 2025 as a 212 MW hybrid project in Des Moines County, IA, according to Berkeley Lab’s queue data file. The filing names Burlington as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of December 31, 2024.

Queue IDR1019
Project nameReplacing 30 MW of existing coal generation with BESS at Burlington Generation Station; Burlington 5
Status (as published)Active
SubstationBurlington
Point of interconnectionBurlington 161kV
CountyDes Moines
StateIA
Voltage161 kV
Capacity212 MW
Resource (as published)Other+Battery
Resource categoryHybrid (normalized for filtering)
Proposed online date2024-12-31
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Des Moines, IA: 10 requests in the MISO queue, 2 active totaling 262 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityAlliant Energy West
Interconnection serviceNRIS
Project typeGeneration
Queue date2022-02-15
Components (hybrid)Other 212 MW + Battery

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first