Replace 330 MW of CLECO.DPS Unit with solar; Dolet Hills (R1004) was listed in the MISO interconnection queue at the end of 2025 as a 330 MW hybrid project in De Soto Parish, LA, according to Berkeley Lab’s queue data file. The filing names Dolet Hills (Bus #) as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of December 31, 2024.
| Queue ID | R1004 |
|---|---|
| Project name | Replace 330 MW of CLECO.DPS Unit with solar; Dolet Hills |
| Status (as published) | Active |
| Substation | Dolet Hills (Bus #) |
| Point of interconnection | Dolet Hills 345 kV (Bus #500260) |
| County | De Soto Parish |
| State | LA |
| Voltage | 345 kV |
| Capacity | 330 MW |
| Resource (as published) | Solar+Other |
| Resource category | Hybrid (normalized for filtering) |
| Proposed online date | 2024-12-31 |
| Source dataset | Berkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025 |
Same substation and county
De Soto Parish, LA: 6 requests in the MISO queue, 3 active totaling 1,185 MW.
Tracked changes
Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.
Additional filed fields
| Utility | CLECO POWER |
|---|---|
| Interconnection service | NRIS |
| Project type | Generation |
| Queue date | 2020-12-30 |
| Components (hybrid) | Solar 330 MW + Other |
Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.
Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.