MISO queue ID J996

Queue request J996 was listed in the MISO interconnection queue at the end of 2025 as a 80 MW solar project in Lenawee County, MI, according to Berkeley Lab’s queue data file. The filing names Beecher - Moraco Line as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of October 31, 2022.

Queue IDJ996
Project nameNot reported
Status (as published)Active
SubstationBeecher - Moraco Line
Point of interconnectionBeecher - Moraco 138kV Line
CountyLenawee
StateMI
Voltage138 kV
Capacity80 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Proposed online date2022-10-31
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Lenawee, MI: 22 requests in the MISO queue, 13 active totaling 2,085 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityMETC
ClusterDPP-2018-APR East (ITC)
Interconnection serviceNRIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)Construction
Study phase (as the queue printed it)Study Phase: GIA; Post GIA Status: Under Construction
Queue date2018-03-12
Interconnection agreement date2021-04-27

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.