Substation Scout

MISO request J993

MISO queue ID J993

Queue request J993 was listed in the MISO interconnection queue at the end of 2025 as a 200 MW solar project in Boone County, IN, according to Berkeley Lab’s queue data file. The filing names Hortonville - Whitestown Line Tap as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of November 1, 2023.

Queue IDJ993
Project nameNot reported
Status (as published)Active
SubstationHortonville - Whitestown Line Tap
Point of interconnectionHortonville - Whitestown 345kV Line Tap
CountyBoone
StateIN
Voltage345 kV
Capacity200 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Proposed online date2023-11-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Boone, IN: 7 requests in the MISO queue, 2 active totaling 510 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityINDIANAPOLIS POWER & LIGHT COMPANY
ClusterDPP-2018-APR Central
Interconnection serviceNRIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)Construction
Study phase (as the queue printed it)Study Phase: GIA; Post GIA Status: Under Construction
Queue date2018-03-12
Interconnection agreement date2021-10-12

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first