Substation Scout

MISO request J868

MISO queue ID J868

Queue request J868 was listed in the MISO interconnection queue at the end of 2025 as a 37.2 MW project in Concordia Parish, LA, according to Berkeley Lab’s queue data file. The filing names Plantation Substation as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of December 3, 1990.

Queue IDJ868
Project nameNot reported
Status (as published)Active
SubstationPlantation Substation
Point of interconnectionPlantation 115 kV Substation
CountyConcordia Parish
StateLA
Voltage115 kV
Capacity37.2 MW
Resource (as published)Other
Resource categoryOther (normalized for filtering)
Proposed online date1990-12-03
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Concordia Parish, LA: 12 requests in the MISO queue, 2 active totaling 237.2 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityEntergy
ClusterDPP-2017-AUG South
Interconnection serviceNRIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)Construction
Study phase (as the queue printed it)Study Phase: GIA; Post GIA Status: Under Construction
Queue date2017-06-16
Interconnection agreement date2020-03-05

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first