Concordia Parish, LA interconnection queue
2 active projects totaling 237.2 MW in the MISO queue, plus 10 with terminal status (shown grayed).
2active projects
237.2active MW
12total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| J1953 | Not reported | 115 | 264.6 | Solar | Withdrawn |
| J2228 | Not reported | n/r | 200 | Solar | Active |
| J2792 | Not reported | 115 | 150 | Solar | Withdrawn |
| J2904 | Not reported | n/r | 150 | Hybrid | Withdrawn |
| J2479 | Not reported | 115 | 140 | Battery | Withdrawn |
| J3046 | Not reported | 115 | 140 | Battery | Withdrawn |
| J565 | Not reported | n/r | 101.8 | Solar | Withdrawn |
| J3272 | Not reported | n/r | 85 | Solar | Withdrawn |
| J2430 | Not reported | 115 | 80 | Solar | Withdrawn |
| J551 | Not reported | n/r | 49.8 | Solar | Withdrawn |
| J868 | Not reported | 115 | 37.2 | Other | Active |
| J635 | Not reported | 115 | 35 | Solar | Withdrawn |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.