Queue request J853 was listed in the MISO interconnection queue at the end of 2025 as a 149 MW solar project in White County, IL, according to Berkeley Lab’s queue data file. The filing names Norris City North Substation Bus as its point of interconnection. Its status as of December 31, 2025 was “Operational”, with a proposed online date of May 28, 2021.
| Queue ID | J853 |
|---|---|
| Project name | Not reported |
| Status (as published) | Operational |
| Substation | Norris City North Substation Bus |
| Point of interconnection | Norris City North Substation 138kV Bus |
| County | White |
| State | IL |
| Voltage | 138 kV |
| Capacity | 149 MW |
| Resource (as published) | Solar |
| Resource category | Solar (normalized for filtering) |
| Proposed online date | 2021-05-28 |
| Source dataset | Berkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025 |
Same substation and county
White, IL: 3 requests in the MISO queue, 3 active totaling 549 MW.
Tracked changes
Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.
Additional filed fields
| Utility | AMEREN ILLINOIS |
|---|---|
| Cluster | DPP-2017-AUG Central |
| Interconnection service | NRIS |
| Project type | Generation |
| Study phase (standardized by Berkeley Lab) | IA Executed |
| Study phase (as the queue printed it) | Study Phase: GIA; Post GIA Status: In Service |
| Queue date | 2017-06-16 |
| Interconnection agreement date | 2019-12-20 |
| Operational date | 2021-05-28 |