Queue request J732 was listed in the MISO interconnection queue at the end of 2025 as a 561.5 MW gas project in Douglas County, WI, according to Berkeley Lab’s queue data file. The filing names Arrowhead - Stone Lake Line as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of November 10, 2023.

Queue IDJ732
Project nameNot reported
Status (as published)Active
SubstationArrowhead - Stone Lake Line
Point of interconnectionArrowhead - Stone Lake 345kV Line
CountyDouglas
StateWI
Voltage345 kV
Capacity561.5 MW
Resource (as published)Gas
Resource categoryGas (normalized for filtering)
Proposed online date2023-11-10
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Douglas, WI: 3 requests in the MISO queue, 1 active totaling 561.5 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityAmerican Transmission Co.
ClusterDPP-2017-AUG East (ATC)
Interconnection serviceNRIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)Construction
Study phase (as the queue printed it)Study Phase: GIA; Post GIA Status: Under Construction
Queue date2017-06-16
Interconnection agreement date2020-07-29

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first