MISO request J590

MISO queue ID J590

Queue request J590 was listed in the MISO interconnection queue at the end of 2025 as a 90 MW wind project in Palo Alto County, IA, according to Berkeley Lab’s queue data file. The filing names Obrien - Kossuth line as its point of interconnection. Its status as of December 31, 2025 was “Operational”, with a proposed online date of October 1, 2019.

Queue IDJ590
Project nameNot reported
Status (as published)Operational
SubstationObrien - Kossuth line
Point of interconnectionObrien - Kossuth 345 kV line
CountyPalo Alto
StateIA
Voltage345 kV
Capacity90 MW
Resource (as published)Wind
Resource categoryWind (normalized for filtering)
Proposed online date2019-10-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Obrien - Kossuth line substation: 2 requests in the MISO queue, 2 active totaling 340 MW.

Queue IDProjectMWResourceStatus
J529Not reported250WindOperational

Palo Alto, IA: 9 requests in the MISO queue, 5 active totaling 990 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

ClusterDPP-2016-AUG West
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Study phase (as the queue printed it)GIA
Queue date2016-05-09
Operational date2019-10-01

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.