MISO request J587

MISO queue ID J587

Queue request J587 was listed in the MISO interconnection queue at the end of 2025 as a 200 MW wind project in Lincoln County, MN, according to Berkeley Lab’s queue data file. The filing names J460 substation on the Brookings-H081 line as its point of interconnection. Its status as of December 31, 2025 was “Operational”, with a proposed online date of September 14, 2020.

Queue IDJ587
Project nameNot reported
Status (as published)Operational
SubstationJ460 substation on the Brookings-H081 line
Point of interconnectionJ460 substation on the Brookings-H081 345kV line
CountyLincoln
StateMN
Voltage345 kV
Capacity200 MW
Resource (as published)Wind
Resource categoryWind (normalized for filtering)
Proposed online date2020-09-14
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Lincoln, MN: 26 requests in the MISO queue, 13 active totaling 1,130 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

ClusterDPP-2016-AUG West
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Study phase (as the queue printed it)GIA
Queue date2016-05-09
Interconnection agreement date2019-09-23
Operational date2020-09-14

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.