MISO request J558

MISO queue ID J558

Queue request J558 was listed in the MISO interconnection queue at the end of 2025 as a 9.2 MW wind project in Pipestone County, MN, according to Berkeley Lab’s queue data file. The filing names Woodstock Tap as its point of interconnection. Its status as of December 31, 2025 was “Operational”, with a proposed online date of September 1, 2017.

Queue IDJ558
Project nameNot reported
Status (as published)Operational
SubstationWoodstock Tap
Point of interconnectionWoodstock Tap 69 kV
CountyPipestone
StateMN
Voltage69 kV
Capacity9.2 MW
Resource (as published)Wind
Resource categoryWind (normalized for filtering)
Proposed online date2017-09-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Pipestone, MN: 23 requests in the MISO queue, 12 active totaling 293.2 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

ClusterMM-2016-AUG WEST
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Study phase (as the queue printed it)DPP - SIS
Queue date2016-04-18
Interconnection agreement date2017-04-17
Operational date2017-09-01

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.