Substation Scout

MISO request J510

MISO queue ID J510

Queue request J510 was listed in the MISO interconnection queue at the end of 2025 as a 284.5 MW gas project in Deuel County, SD, according to Berkeley Lab’s queue data file. The filing names Scandinavia Township 113N, Range 48W as its point of interconnection. Its status as of December 31, 2025 was “Operational”, with a proposed online date of September 30, 2018.

Queue IDJ510
Project nameNot reported
Status (as published)Operational
SubstationScandinavia Township 113N, Range 48W
Point of interconnectionScandinavia Township 113N, Range 48W
CountyDeuel
StateSD
VoltageNot reported
Capacity284.5 MW
Resource (as published)Gas
Resource categoryGas (normalized for filtering)
Proposed online date2018-09-30
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Deuel, SD: 23 requests in the MISO queue, 6 active totaling 2,320.7 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

ClusterDPP-2016-FEB West
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Study phase (as the queue printed it)GIA
Queue date2015-11-16
Interconnection agreement date2018-12-19
Operational date2018-09-30

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.