Queue request J493 was listed in the MISO interconnection queue at the end of 2025 as a 150 MW wind project in Yellow Medicine County, MN, according to Berkeley Lab’s queue data file. The filing names Big Stone - Brookings Substation as its point of interconnection. Its status as of December 31, 2025 was “Operational”, with a proposed online date of April 30, 2020.

Queue IDJ493
Project nameNot reported
Status (as published)Operational
SubstationBig Stone - Brookings Substation
Point of interconnectionBig Stone - Brookings 345 kV Substation
CountyYellow Medicine
StateMN
Voltage345 kV
Capacity150 MW
Resource (as published)Wind
Resource categoryWind (normalized for filtering)
Proposed online date2020-04-30
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Yellow Medicine, MN: 13 requests in the MISO queue, 4 active totaling 518 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

ClusterDPP-2016-FEB West
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Study phase (as the queue printed it)GIA
Queue date2015-11-12
Interconnection agreement date2019-03-19
Operational date2020-04-30

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.