Substation Scout

MISO request J486

MISO queue ID J486

Queue request J486 was listed in the MISO interconnection queue at the end of 2025 as a 51 MW gas project in Grimes County, TX, according to Berkeley Lab’s queue data file. The filing names Grimes Substation as its point of interconnection. Its status as of December 31, 2025 was “Operational”, with a proposed online date of September 19, 2000.

Queue IDJ486
Project nameNot reported
Status (as published)Operational
SubstationGrimes Substation
Point of interconnectionGrimes 345kV Substation
CountyGrimes
StateTX
Voltage345 kV
Capacity51 MW
Resource (as published)Gas
Resource categoryGas (normalized for filtering)
Proposed online date2000-09-19
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Grimes Substation substation: 2 requests in the MISO queue, 1 active totaling 51 MW.

Queue IDProjectMWResourceStatus
J1100Not reported200SolarWithdrawn

Grimes, TX: 4 requests in the MISO queue, 1 active totaling 51 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

ClusterDPP-2016-FEB South
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Study phase (as the queue printed it)GIA
Queue date2015-10-22
Interconnection agreement date2017-05-22
Operational date2000-09-19

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first