MISO request J481
MISO queue ID J481
Queue request J481 was listed in the MISO interconnection queue at the end of 2025 as a 134.8 MW gas project in Orleans Parish, LA, according to Berkeley Lab’s queue data file. The filing names Existing Michoud Power Station as its point of interconnection. Its status as of December 31, 2025 was “Operational”, with a proposed online date of July 25, 2019.
| Queue ID | J481 |
|---|---|
| Project name | Not reported |
| Status (as published) | Operational |
| Substation | Existing Michoud Power Station |
| Point of interconnection | Existing Michoud Power Station |
| County | Orleans Parish |
| State | LA |
| Voltage | Not reported |
| Capacity | 134.8 MW |
| Resource (as published) | Gas |
| Resource category | Gas (normalized for filtering) |
| Proposed online date | 2019-07-25 |
| Source dataset | Berkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025 |
Same substation and county
Orleans Parish, LA: 5 requests in the MISO queue, 2 active totaling 174.8 MW.
Tracked changes
Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.
Additional filed fields
| Cluster | DPP-2016-AUG South |
|---|---|
| Project type | Generation |
| Study phase (standardized by Berkeley Lab) | IA Executed |
| Study phase (as the queue printed it) | GIA |
| Queue date | 2015-09-14 |
| Operational date | 2019-07-25 |
Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.
Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.