MISO request J472
MISO queue ID J472
Queue request J472 was listed in the MISO interconnection queue at the end of 2025 as a 1,044.8 MW gas project in Montgomery County, TX, according to Berkeley Lab’s queue data file. The filing names Entergy√¢‚Ǩ‚Ñ¢s and Lewis Creek Substations as its point of interconnection. Its status as of December 31, 2025 was “Operational”, with a proposed online date of July 1, 2020.
| Queue ID | J472 |
|---|---|
| Project name | Not reported |
| Status (as published) | Operational |
| Substation | Entergy’s and Lewis Creek Substations |
| Point of interconnection | Entergy’s 138 kV and 230kV Lewis Creek Substations |
| County | Montgomery |
| State | TX |
| Voltage | 138 kV |
| Capacity | 1,044.8 MW |
| Resource (as published) | Gas |
| Resource category | Gas (normalized for filtering) |
| Proposed online date | 2020-07-01 |
| Source dataset | Berkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025 |
Same substation and county
Montgomery, TX: 4 requests in the MISO queue, 2 active totaling 1,250.6 MW.
Tracked changes
Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.
Additional filed fields
| Cluster | DPP-2016-AUG South |
|---|---|
| Project type | Generation |
| Study phase (standardized by Berkeley Lab) | IA Executed |
| Study phase (as the queue printed it) | GIA |
| Queue date | 2015-09-10 |
| Interconnection agreement date | 2018-07-27 |
| Operational date | 2020-07-01 |
Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.
Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.