MISO queue ID J468

Queue request J468 was listed in the MISO interconnection queue at the end of 2025 as a 202 MW wind project in Douglas County, IL, according to Berkeley Lab’s queue data file. The filing names Along existing Sidney-Kansas West line as its point of interconnection. Its status as of December 31, 2025 was “Operational”, with a proposed online date of May 1, 2019.

Queue IDJ468
Project nameNot reported
Status (as published)Operational
SubstationAlong existing Sidney-Kansas West line
Point of interconnectionAlong existing Sidney-Kansas West 345 kV line
CountyDouglas
StateIL
Voltage345 kV
Capacity202 MW
Resource (as published)Wind
Resource categoryWind (normalized for filtering)
Proposed online date2019-05-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Douglas, IL: 4 requests in the MISO queue, 1 active totaling 202 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

ClusterDPP-2016-FEB Central
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Study phase (as the queue printed it)GIA
Queue date2015-06-25
Interconnection agreement date2017-06-12
Operational date2019-05-01

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.