MISO request J438
MISO queue ID J438
Queue request J438 was listed in the MISO interconnection queue at the end of 2025 as a 170 MW wind project in Poweshiek County, IA, according to Berkeley Lab’s queue data file. The filing names Poweshiek-Parnell line as its point of interconnection. Its status as of December 31, 2025 was “Operational”, with a proposed online date of December 15, 2018.
| Queue ID | J438 |
|---|---|
| Project name | Not reported |
| Status (as published) | Operational |
| Substation | Poweshiek-Parnell line |
| Point of interconnection | Poweshiek-Parnell 161 kV line |
| County | Poweshiek |
| State | IA |
| Voltage | 161 kV |
| Capacity | 170 MW |
| Resource (as published) | Wind |
| Resource category | Wind (normalized for filtering) |
| Proposed online date | 2018-12-15 |
| Source dataset | Berkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025 |
Same substation and county
Poweshiek, IA: 5 requests in the MISO queue, 3 active totaling 510 MW.
Tracked changes
Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.
Additional filed fields
| Cluster | DPP-2015-AUG West |
|---|---|
| Project type | Generation |
| Study phase (standardized by Berkeley Lab) | IA Executed |
| Study phase (as the queue printed it) | DPP - SIS |
| Queue date | 2015-03-16 |
| Interconnection agreement date | 2017-09-05 |
| Operational date | 2018-12-15 |
Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.
Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.