Queue request J438 was listed in the MISO interconnection queue at the end of 2025 as a 170 MW wind project in Poweshiek County, IA, according to Berkeley Lab’s queue data file. The filing names Poweshiek-Parnell line as its point of interconnection. Its status as of December 31, 2025 was “Operational”, with a proposed online date of December 15, 2018.

Queue IDJ438
Project nameNot reported
Status (as published)Operational
SubstationPoweshiek-Parnell line
Point of interconnectionPoweshiek-Parnell 161 kV line
CountyPoweshiek
StateIA
Voltage161 kV
Capacity170 MW
Resource (as published)Wind
Resource categoryWind (normalized for filtering)
Proposed online date2018-12-15
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Poweshiek, IA: 5 requests in the MISO queue, 3 active totaling 510 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

ClusterDPP-2015-AUG West
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Study phase (as the queue printed it)DPP - SIS
Queue date2015-03-16
Interconnection agreement date2017-09-05
Operational date2018-12-15

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first