Substation Scout

MISO request J4189

MISO queue ID J4189

Queue request J4189 was listed in the MISO interconnection queue at the end of 2025 as a 200 MW solar project in Sunflower County, MS, according to Berkeley Lab’s queue data file. The filing names ROUNDAWAY SS (CE) - CLARKSDALE as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of April 1, 2030.

Queue IDJ4189
Project nameNot reported
Status (as published)Active
SubstationROUNDAWAY SS (CE) - CLARKSDALE
Point of interconnectionROUNDAWAY SS (CE) - CLARKSDALE 115.0kV
CountySunflower
StateMS
Voltage115 kV
Capacity200 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Proposed online date2030-04-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Sunflower, MS: 25 requests in the MISO queue, 11 active totaling 1,669 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityENTERGY MISSISSIPPI, LLC.
ClusterDPP Cycle Pending South
Interconnection serviceNRIS
Project typeGeneration
Queue date2025-10-06

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first