Substation Scout

MISO request J4150

MISO queue ID J4150

Queue request J4150 was listed in the MISO interconnection queue at the end of 2025 as a 42.2 MW solar project in Cass County, IA, according to Berkeley Lab’s queue data file. The filing names ATLANTIC - ADAIR as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of September 1, 2027.

Queue IDJ4150
Project nameNot reported
Status (as published)Active
SubstationATLANTIC - ADAIR
Point of interconnectionATLANTIC - ADAIR 161.0kV
CountyCass
StateIA
Voltage161 kV
Capacity42.2 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Proposed online date2027-09-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Cass, IA: 5 requests in the MISO queue, 4 active totaling 237.4 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityMISSOURI RIVER ENERGY SERVICES - TRANSMISSION
ClusterDPP Cycle Pending West
Interconnection serviceNRIS
Project typeGeneration
Queue date2025-10-06

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first