Substation Scout

MISO request J4142

MISO queue ID J4142

Queue request J4142 was listed in the MISO interconnection queue at the end of 2025 as a 115 MW solar project in Franklin Parish, LA, according to Berkeley Lab’s queue data file. The filing names Gilbert as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of August 31, 2030.

Queue IDJ4142
Project nameNot reported
Status (as published)Active
SubstationGilbert
Point of interconnectionGilbert 115 kV
CountyFranklin Parish
StateLA
Voltage115 kV
Capacity115 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Proposed online date2030-08-31
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Franklin Parish, LA: 7 requests in the MISO queue, 3 active totaling 355 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityENTERGY LOUISIANA
ClusterDPP Cycle Pending South
Interconnection serviceNRIS
Project typeGeneration
Queue date2025-10-04

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.