Franklin Parish, LA interconnection queue

3 active projects totaling 355 MW in the MISO queue, plus 4 with terminal status (shown grayed).

3active projects
355active MW
7total filed
Queue IDProjectkVMWResourceStatus
J2385 Not reported 115 179 Solar Withdrawn
J3082 Not reported 115 135 Hybrid Active
J4142 Not reported 115 115 Solar Active
J2693 Not reported n/r 105 Solar Active
J3098 Not reported 115 75 Solar Withdrawn
J618 Not reported n/r 58.7 Solar Withdrawn
J659 Not reported 115 50 Solar Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.