Substation Scout

MISO request J4140

MISO queue ID J4140

Queue request J4140 was listed in the MISO interconnection queue at the end of 2025 as a 100 MW battery project in Ouachita Parish, LA, according to Berkeley Lab’s queue data file. The filing names Cotton as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of May 31, 2030.

Queue IDJ4140
Project nameNot reported
Status (as published)Active
SubstationCotton
Point of interconnectionCotton
CountyOuachita Parish
StateLA
VoltageNot reported
Capacity100 MW
Resource (as published)Battery
Resource categoryBattery (normalized for filtering)
Proposed online date2030-05-31
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Ouachita Parish, LA: 16 requests in the MISO queue, 9 active totaling 1,705 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityENTERGY LOUISIANA
ClusterDPP Cycle Pending South
Interconnection serviceNRIS
Project typeGeneration
Queue date2025-09-25

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first