Substation Scout

MISO request J4127

MISO queue ID J4127

Queue request J4127 was listed in the MISO interconnection queue at the end of 2025 as a 100 MW solar project in Barron County, WI, according to Berkeley Lab’s queue data file. The filing names Ridgeland as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of January 19, 2029.

Queue IDJ4127
Project nameNot reported
Status (as published)Active
SubstationRidgeland
Point of interconnectionRidgeland
CountyBarron
StateWI
VoltageNot reported
Capacity100 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Proposed online date2029-01-19
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Barron, WI: 5 requests in the MISO queue, 4 active totaling 495 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityNORTHERN STATES POWER COMPANY
ClusterDPP Cycle Pending West
Interconnection serviceNRIS
Project typeGeneration
Queue date2025-09-18

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.