Substation Scout

MISO request J4118

MISO queue ID J4118

Queue request J4118 was listed in the MISO interconnection queue at the end of 2025 as a 250 MW battery project in Mclean County, IL, according to Berkeley Lab’s queue data file. The filing names Radbourn (LRTP-41) as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of September 30, 2030.

Queue IDJ4118
Project nameNot reported
Status (as published)Active
SubstationRadbourn (LRTP-41)
Point of interconnectionRadbourn 345kV (LRTP-41)
CountyMclean
StateIL
Voltage345 kV
Capacity250 MW
Resource (as published)Battery
Resource categoryBattery (normalized for filtering)
Proposed online date2030-09-30
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Mclean, IL: 27 requests in the MISO queue, 11 active totaling 2,233 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

ClusterDPP Cycle Pending Central
Interconnection serviceNRIS
Project typeGeneration
Queue date2025-09-24

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first