MISO queue ID J4116

Queue request J4116 was listed in the MISO interconnection queue at the end of 2025 as a 950 MW gas project in Walworth County, WI, according to Berkeley Lab’s queue data file. The filing names Sugar Creek as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of December 31, 2030.

Queue IDJ4116
Project nameNot reported
Status (as published)Active
SubstationSugar Creek
Point of interconnectionSugar Creek 345 kV
CountyWalworth
StateWI
Voltage345 kV
Capacity950 MW
Resource (as published)Gas
Resource categoryGas (normalized for filtering)
Proposed online date2030-12-31
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Walworth, WI: 16 requests in the MISO queue, 3 active totaling 1,374 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityAMERICAN TRANSMISSION COMPANY
ClusterDPP Cycle Pending East (ATC)
Interconnection serviceNRIS
Project typeGeneration
Queue date2025-10-06

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first