Substation Scout

Walworth, WI interconnection queue

3 active projects totaling 1,374 MW in the MISO queue, plus 13 with terminal status (shown grayed).

3active projects
1,374active MW
16total filed
Queue IDProjectkVMWResourceStatus
J4116 Not reported 345 950 Gas Active
G138 Not reported n/r 352 Other Withdrawn
J4028 Not reported 138 324 Gas Active
J1042 Not reported 138 200 Solar Withdrawn
J1044 Not reported 138 200 Solar Withdrawn
J1047 Not reported 138 200 Solar Withdrawn
J798 Not reported n/r 124 Solar Withdrawn
G288 Not reported n/r 100 Wind Withdrawn
G379 Not reported n/r 100 Wind Withdrawn
G546 Not reported 138 100 Wind Withdrawn
J1740 Not reported 138 100 Solar Withdrawn
J1955 Not reported 138 100 Solar Withdrawn
J2666 Not reported 138 100 Solar Active
J892 Not reported 138 75 Solar Withdrawn
G956 Not reported 69 50 Wind Withdrawn
J1954 Not reported 138 35 Battery Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →