Substation Scout

MISO request J4115

MISO queue ID J4115

Queue request J4115 was listed in the MISO interconnection queue at the end of 2025 as a 525 MW gas project in Fond Du Lac County, WI, according to Berkeley Lab’s queue data file. The filing names South Fond du Lac - Fitzgerald as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of June 30, 2028.

Queue IDJ4115
Project nameNot reported
Status (as published)Active
SubstationSouth Fond du Lac - Fitzgerald
Point of interconnectionSouth Fond du Lac - Fitzgerald 345.0kV
CountyFond Du Lac
StateWI
Voltage345 kV
Capacity525 MW
Resource (as published)Gas
Resource categoryGas (normalized for filtering)
Proposed online date2028-06-30
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

South Fond du Lac - Fitzgerald substation: 2 requests in the MISO queue, 1 active totaling 525 MW.

Queue IDProjectMWResourceStatus
J1716Not reported100SolarWithdrawn

Fond Du Lac, WI: 14 requests in the MISO queue, 6 active totaling 951 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityAMERICAN TRANSMISSION COMPANY
ClusterDPP Cycle Pending East (ATC)
Interconnection serviceNRIS
Project typeGeneration
Queue date2025-10-06

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first