Queue request J4095 was listed in the MISO interconnection queue at the end of 2025 as a 300 MW battery project in Huron County, MI, according to Berkeley Lab’s queue data file. The filing names GRASSMERE as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of June 30, 2030.

Queue IDJ4095
Project nameNot reported
Status (as published)Active
SubstationGRASSMERE
Point of interconnectionGRASSMERE
CountyHuron
StateMI
VoltageNot reported
Capacity300 MW
Resource (as published)Battery
Resource categoryBattery (normalized for filtering)
Proposed online date2030-06-30
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

GRASSMERE substation: 4 requests in the MISO queue, 4 active totaling 1,280 MW.

Queue IDProjectMWResourceStatus
J3966Not reported480WindActive
J4094Not reported300BatteryActive
J1525Not reported200SolarActive

Huron, MI: 41 requests in the MISO queue, 29 active totaling 4,917.9 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityITC
ClusterDPP Cycle Pending East (ITC)
Interconnection serviceNRIS
Project typeGeneration
Queue date2025-10-06

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.