MISO request J4088
MISO queue ID J4088
Queue request J4088 was listed in the MISO interconnection queue at the end of 2025 as a 340 MW hybrid project in Lee County, AR, according to Berkeley Lab’s queue data file. The filing names Wheatley Switching Station (being built by J1710 & J1820) as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of March 1, 2028.
| Queue ID | J4088 |
|---|---|
| Project name | Not reported |
| Status (as published) | Active |
| Substation | Wheatley Switching Station (being built by J1710 & J1820) |
| Point of interconnection | Wheatley 500 kV Switching Station (being built by J1710 & J1820) |
| County | Lee |
| State | AR |
| Voltage | 500 kV |
| Capacity | 340 MW |
| Resource (as published) | Solar+Battery |
| Resource category | Hybrid (normalized for filtering) |
| Proposed online date | 2028-03-01 |
| Source dataset | Berkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025 |
Same substation and county
Lee, AR: 18 requests in the MISO queue, 7 active totaling 1,600 MW.
Tracked changes
Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.
Additional filed fields
| Utility | ENTERGY ARKANSAS |
|---|---|
| Cluster | DPP Cycle Pending South |
| Interconnection service | NRIS |
| Project type | Generation |
| Queue date | 2025-10-06 |
| Components (hybrid) | Solar 340 MW + Battery |
Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.
Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.