Substation Scout

MISO request J4075

MISO queue ID J4075

Queue request J4075 was listed in the MISO interconnection queue at the end of 2025 as a 300 MW battery project in St. Landry Parish, LA, according to Berkeley Lab’s queue data file. The filing names Ville Platte - West Fork as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of June 30, 2030.

Queue IDJ4075
Project nameNot reported
Status (as published)Active
SubstationVille Platte - West Fork
Point of interconnectionVille Platte - West Fork 230.0kV
CountySt. Landry Parish
StateLA
Voltage230 kV
Capacity300 MW
Resource (as published)Battery
Resource categoryBattery (normalized for filtering)
Proposed online date2030-06-30
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Ville Platte - West Fork substation: 4 requests in the MISO queue, 3 active totaling 655.5 MW.

Queue IDProjectMWResourceStatus
J3368Not reported199.9WindActive
J3394Not reported155.6WindActive
J2135Not reported200SolarWithdrawn

St. Landry Parish, LA: 11 requests in the MISO queue, 7 active totaling 1,412.6 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityCLECO POWER
ClusterDPP Cycle Pending South
Interconnection serviceNRIS
Project typeGeneration
Queue date2025-10-06

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.