Substation Scout

MISO request J406

MISO queue ID J406

Queue request J406 was listed in the MISO interconnection queue at the end of 2025 as a 4 MW project in Wexford County, MI, according to Berkeley Lab’s queue data file. The filing names Wexford Substation as its point of interconnection. Its status as of December 31, 2025 was “Operational”, with a proposed online date of January 1, 2018.

Queue IDJ406
Project nameNot reported
Status (as published)Operational
SubstationWexford Substation
Point of interconnectionWexford Substation
CountyWexford
StateMI
VoltageNot reported
Capacity4 MW
Resource (as published)Other
Resource categoryOther (normalized for filtering)
Proposed online date2018-01-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Wexford, MI: 3 requests in the MISO queue, 2 active totaling 304 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

ClusterDPP-2015-FEB East (ITC)
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Study phase (as the queue printed it)Int FaS
Queue date2014-11-14
Interconnection agreement date2016-05-02
Operational date2018-01-01

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.