Substation Scout

MISO request J4057

MISO queue ID J4057

Queue request J4057 was listed in the MISO interconnection queue at the end of 2025 as a 127.4 MW solar project in Mower County, MN, according to Berkeley Lab’s queue data file. The filing names YANKEE as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of May 30, 2030.

Queue IDJ4057
Project nameNot reported
Status (as published)Active
SubstationYANKEE
Point of interconnectionYANKEE
CountyMower
StateMN
VoltageNot reported
Capacity127.4 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Proposed online date2030-05-30
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

YANKEE substation: 2 requests in the MISO queue, 2 active totaling 372.4 MW.

Queue IDProjectMWResourceStatus
J3961Not reported245SolarActive

Mower, MN: 39 requests in the MISO queue, 12 active totaling 2,228.4 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityNORTHERN STATES POWER COMPANY
ClusterDPP Cycle Pending West
Interconnection serviceNRIS
Project typeGeneration
Queue date2025-08-22

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first