Queue request J4041 was listed in the MISO interconnection queue at the end of 2025 as a 220 MW solar project in Menard County, IL, according to Berkeley Lab’s queue data file. The filing names Shockey as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of November 1, 2030.

Queue IDJ4041
Project nameNot reported
Status (as published)Active
SubstationShockey
Point of interconnectionShockey
CountyMenard
StateIL
VoltageNot reported
Capacity220 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Proposed online date2030-11-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Shockey substation: 3 requests in the MISO queue, 2 active totaling 420 MW.

Queue IDProjectMWResourceStatus
J1831Not reported200WindActive
J3087Not reported204.6BatteryWithdrawn

Menard, IL: 2 requests in the MISO queue, 2 active totaling 420 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityAMEREN ILLINOIS
ClusterDPP Cycle Pending Central
Interconnection serviceNRIS
Project typeGeneration
Queue date2025-06-12

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first