MISO request J3953
MISO queue ID J3953
Queue request J3953 was listed in the MISO interconnection queue at the end of 2025 as a 90 MW solar project in Faulkner County, AR, according to Berkeley Lab’s queue data file. The filing names BONO - GREENBRIER as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of December 15, 2028.
| Queue ID | J3953 |
|---|---|
| Project name | Not reported |
| Status (as published) | Active |
| Substation | BONO - GREENBRIER |
| Point of interconnection | BONO - GREENBRIER 161.0kV |
| County | Faulkner |
| State | AR |
| Voltage | 161 kV |
| Capacity | 90 MW |
| Resource (as published) | Solar |
| Resource category | Solar (normalized for filtering) |
| Proposed online date | 2028-12-15 |
| Source dataset | Berkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025 |
Same substation and county
Faulkner, AR: 4 requests in the MISO queue, 2 active totaling 290 MW.
Tracked changes
Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.
Additional filed fields
| Utility | ENTERGY ARKANSAS |
|---|---|
| Cluster | DPP Cycle Pending South |
| Interconnection service | NRIS |
| Project type | Generation |
| Queue date | 2024-11-05 |
Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.
Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.