Substation Scout

MISO request J3946

MISO queue ID J3946

Queue request J3946 was listed in the MISO interconnection queue at the end of 2025 as a 300 MW battery project in Tazewell County, IL, according to Berkeley Lab’s queue data file. The filing names Tazewell as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of June 1, 2030.

Queue IDJ3946
Project nameNot reported
Status (as published)Active
SubstationTazewell
Point of interconnectionTazewell
CountyTazewell
StateIL
VoltageNot reported
Capacity300 MW
Resource (as published)Battery
Resource categoryBattery (normalized for filtering)
Proposed online date2030-06-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Tazewell, IL: 19 requests in the MISO queue, 11 active totaling 1,743 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

ClusterDPP Cycle Pending Central
Interconnection serviceNRIS
Project typeGeneration
Queue date2025-03-31

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.