MISO queue ID J3914

Queue request J3914 was listed in the MISO interconnection queue at the end of 2025 as a 85 MW solar project in Jefferson Davis Parish, LA, according to Berkeley Lab’s queue data file. The filing names COMPTON CO as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of September 2, 2030.

Queue IDJ3914
Project nameNot reported
Status (as published)Active
SubstationCOMPTON CO
Point of interconnectionCOMPTON CO
CountyJefferson Davis Parish
StateLA
VoltageNot reported
Capacity85 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Proposed online date2030-09-02
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Jefferson Davis Parish, LA: 20 requests in the MISO queue, 9 active totaling 1,640 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

ClusterDPP Cycle Pending South
Interconnection serviceNRIS
Project typeGeneration
Queue date2024-10-25

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.