MISO request J3913
MISO queue ID J3913
Queue request J3913 was listed in the MISO interconnection queue at the end of 2025 as a 140 MW solar project in Amite County, MS, according to Berkeley Lab’s queue data file. The filing names GLOSTER - LIBERTY as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of September 2, 2030.
| Queue ID | J3913 |
|---|---|
| Project name | Not reported |
| Status (as published) | Active |
| Substation | GLOSTER - LIBERTY |
| Point of interconnection | GLOSTER - LIBERTY 115.0kV |
| County | Amite |
| State | MS |
| Voltage | 115 kV |
| Capacity | 140 MW |
| Resource (as published) | Solar |
| Resource category | Solar (normalized for filtering) |
| Proposed online date | 2030-09-02 |
| Source dataset | Berkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025 |
Same substation and county
GLOSTER - LIBERTY substation: 2 requests in the MISO queue, 2 active totaling 240 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| J3231 | Not reported | 100 | Hybrid | Active |
Amite, MS: 9 requests in the MISO queue, 3 active totaling 405 MW.
Tracked changes
Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.
Additional filed fields
| Utility | ENTERGY MISSISSIPPI, LLC. |
|---|---|
| Cluster | DPP Cycle Pending South |
| Interconnection service | NRIS |
| Project type | Generation |
| Queue date | 2024-10-25 |
Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.
Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.