MISO request J3901

MISO queue ID J3901

Queue request J3901 was listed in the MISO interconnection queue at the end of 2025 as a 300 MW wind project in Shelby County, IL, according to Berkeley Lab’s queue data file. The filing names 4MATOONW S - 4NEOGA 3 as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of April 1, 2030.

Queue IDJ3901
Project nameNot reported
Status (as published)Active
Substation4MATOONW S - 4NEOGA 3
Point of interconnection4MATOONW S - 4NEOGA 3 138.0kV
CountyShelby
StateIL
Voltage138 kV
Capacity300 MW
Resource (as published)Wind
Resource categoryWind (normalized for filtering)
Proposed online date2030-04-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Shelby, IL: 13 requests in the MISO queue, 7 active totaling 1,275 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityAMEREN ILLINOIS
ClusterDPP Cycle Pending Central
Interconnection serviceNRIS
Project typeGeneration
Queue date2025-01-17

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first