MISO queue ID J3861

Queue request J3861 was listed in the MISO interconnection queue at the end of 2025 as a 100 MW battery project in Branch County, MI, according to Berkeley Lab’s queue data file. The filing names WAGNER as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of July 28, 2028.

Queue IDJ3861
Project nameNot reported
Status (as published)Active
SubstationWAGNER
Point of interconnectionWAGNER
CountyBranch
StateMI
VoltageNot reported
Capacity100 MW
Resource (as published)Battery
Resource categoryBattery (normalized for filtering)
Proposed online date2028-07-28
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

WAGNER substation: 2 requests in the MISO queue, 2 active totaling 300 MW.

Queue IDProjectMWResourceStatus
J4123Not reported200BatteryActive

Branch, MI: 17 requests in the MISO queue, 13 active totaling 3,125 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityMETC
ClusterDPP Cycle Pending East (ITC)
Interconnection serviceNRIS
Project typeGeneration
Queue date2024-12-13

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first