MISO request J3853

MISO queue ID J3853

Queue request J3853 was listed in the MISO interconnection queue at the end of 2025 as a 300 MW wind project in Iroquois County, IL, according to Berkeley Lab’s queue data file. The filing names Other_ as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of June 1, 2029.

Queue IDJ3853
Project nameNot reported
Status (as published)Active
SubstationOther_
Point of interconnectionOther_
CountyIroquois
StateIL
VoltageNot reported
Capacity300 MW
Resource (as published)Wind
Resource categoryWind (normalized for filtering)
Proposed online date2029-06-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Other_ substation: 112 requests in the MISO queue, 60 active totaling 15,611.7 MW.

Queue IDProjectMWResourceStatus
J4024Not reported1,499GasActive
J4025Not reported1,499GasActive
J4165Not reported1,203GasActive
J2690Not reported500HybridActive
J3931Not reported500SolarActive
J4082Not reported500BatteryActive
J3991Not reported340WindActive
J3412Not reported300SolarActive
J3758Not reported300SolarActive
J3910Not reported300WindActive
J3957Not reported300SolarActive
J3564Not reported275WindActive

99 more on the substation page.

Iroquois, IL: 13 requests in the MISO queue, 9 active totaling 1,927.9 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityAMEREN ILLINOIS
ClusterDPP Cycle Pending Central
Interconnection serviceNRIS
Project typeGeneration
Queue date2024-12-26

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.